Zuellig Pharma Limited

  • Writer: WYE
    WYE
  • Feb 27
  • 1 min read

Location: 1/F., GOODMAN WESTLINK, 8 SIU LANG SHUI ROAD, TUEN MUN, N.T.


WYE shall be responsible for the extension of the conveyor system from the existing line to 6 new outflow lanes, covering design, site survey, material procurement, installation, testing and commissioning. We will also audit the existing PLC logic and configure the new conveyor I/O signals, while ensuring operational continuity throughout the works.

We provide a comprehensive one-stop service to fully meet the client’s requirements.

With the system upgraded via PLC logic control, the production operation will be highly reliable and easy to maintain.

Ultimately, this will reduce operating costs and improve overall productivity.